High Schools Established Details

PTSMC Notified
Acheived: 25
Total Target: 25
Percent Acheived: 100%
Land Mutation Completed
Acheived: 25
Year Target: 25
Percent Acheived: 100%
Teacher's Employed
Acheived: 25
Year Target: 25
Percent Acheived: 100%
Construction Works Started
Acheived: 24
Year Target: 25
Percent Acheived: 96%
Science Labortary
Acheived: 24
Year Target: 25
Percent Acheived: 96%
ICT Supply
Acheived: 22
Year Target: 25
Percent Acheived: 88%